SUNBURY PRIMARY SCHOOL
Setout and preps for our library slab at Sunbury Primary School. N12 bar at 250 centre’s top and bottom right through this one as well as plenty of processed bar for cages, cogged top bar details, Z-bars etc. Quite a lot of formwork and good variety of slab edge details both over blockwork and in ground, a drip line detail as well.
500m2 multipurpose room slab set up and ready for a pour at Sunbury Primary School once we get the all clear that lockdown is coming to an end. Been a big start to the year at Concrete Creations and a great effort from everyone to keep things ticking along with everything that is going on externally. We have to work with the hand we are dealt and just keep control of what we can control.